Project Timeline
Timeline Overview
June 2020
- Continue Dam Rehabilitation Design Approach Refinement
- Dredging Design
- Field Work Tasks for Freshwater Mussel Survey
- Bathymetric Survey
- Cultural Resources
- Topographic Survey
- Geotechnical Investigation
Late Summer 2020
- August 2020 Meeting with Bachman Lake Stakeholders (Friends of Bachman Lake) to present project overview and gather input.
Winter 2020/2021
- Complete Dam Rehabilitation Design Basis Report
- Public & Bachman Lake Stakeholders Meeting to present Project Update – February 8, 2021 with Friends of Bachman Lake (FoBL)
Spring 2021
- Complete Dredging Design and Advertisement for Dredging Bids
Summer 2021
- Begin Final Design Phase of Dam Rehabilitation
- Open Bids for Dredging Services
Fall 2021
- Council Consideration of Dredging Construction Contract
Winter 2021/2022
- Begin Bachman Lake Dredging Work
- Public & Bachman Lake Stakeholders Meeting to present Project Update – Met with Friends of Bachman Lake (FoBL) on February 2, 2022
Spring 2023
- Complete Dam Rehabilitation Design and Advertisement for Bids
- Completion of Bachman Lake Dredging and Demobilization
Fall 2023
- Bachman Lake Community/Stakeholders Meeting to present Project Update
Late Summer/Early Fall 2023
- Council Consideration of Dam Rehabilitation Construction Contract
Winter 2023/2024
- Begin Dam Rehabilitation Construction
Winter 2025/2026
- Completion of Dam Rehabilitation Construction and Demobilization